November 28 - December 2, 2022

  • Deck shoring complete at Level 24

  • Deck concrete placement at Level 24 to occur on 12/9/22

  • MEPF rough-in in progress through Level 23

  • Window Wall in progress at Level 16

  • Metal framing in progress at Level 15

  • Drywall pre-hang in progress at residential units Level 13

  • MEP wall and ceiling rough-in at residential units Level 12