October 10-14, 2022Deck shoring complete at Level 19Deck concrete placement at Level 19 to occur on 10/17/22MEPF rough-in in progress at Level 19Window Wall in progress at Level 11Metal framing in progress at Level 10
Deck shoring complete at Level 19Deck concrete placement at Level 19 to occur on 10/17/22MEPF rough-in in progress at Level 19Window Wall in progress at Level 11Metal framing in progress at Level 10