October 10-14, 2022

  • Deck shoring complete at Level 19

  • Deck concrete placement at Level 19 to occur on 10/17/22

  • MEPF rough-in in progress at Level 19

  • Window Wall in progress at Level 11

  • Metal framing in progress at Level 10