October 11-15, 2021

  • Deck Shoring started at Level 1 Area 1

  • Rebar & MEP rough in ongoing at Level P1 Area 3

  • Concrete pour for Level P1 Area 3 scheduled for 10/20/21

  • Perimeter walls, columns & shear walls in progress at Level P1 Area 1

  • Waterproofing being installed up to grade at North elevation

  • CMU walls ongoing at Garage Levels P4 & P5