October 16 - 20, 2023

  • Window Wall in progress at Level 37

  • Metal framing in progress at Level 37

  • Unit tape and finish in progress at Level 34

  • Unit paint in progress at Level 32

  • Unit cabinets in progress at Level 30

  • Unit Bath/Shower surround tile in progress at Level 31

  • Unit countertops in progress at Level 26

  • Unit LVP flooring in progress at Level 24

  • Unite appliances in progress at Level 21

  • Taping in progress at Level 9 Amenities

  • Framing in progress at Level 37 Amenities