October 17-21, 2022

  • Deck shoring complete at Level 20

  • Deck concrete placement at Level 20 to occur on 10/25/22

  • MEPF rough-in in progress at Level 20

  • Window Wall in progress at Level 12

  • Metal framing in progress at Level 10