October 17-21, 2022Deck shoring complete at Level 20Deck concrete placement at Level 20 to occur on 10/25/22MEPF rough-in in progress at Level 20Window Wall in progress at Level 12Metal framing in progress at Level 10
Deck shoring complete at Level 20Deck concrete placement at Level 20 to occur on 10/25/22MEPF rough-in in progress at Level 20Window Wall in progress at Level 12Metal framing in progress at Level 10