October 2 - 6, 2023

  • Window Wall in progress at Level 37

  • Metal framing in progress at Level 37

  • Unit tape and finish in progress at Level 33

  • Unit paint in progress at Level 31

  • Unit cabinets in progress at Level 29

  • Unit Bath/Shower surround tile in progress at Level 30

  • Unit countertops in progress at Level 25

  • Unit LVP flooring in progress at Level 23

  • Residential Unit Finishes in progress at Level 10

  • Rough clean in progress at Levell 13 Residential Units

  • Drywall in progress at Level 9 Amenities

  • Framing in progress at Level 37 Amenities