Deck shoring in progress at Level 21
Deck concrete placement at Level 21 to occur on 11/2/22
MEPF rough-in in progress at Level 21
Window Wall in progress at Level 13
Metal framing in progress at Level 12
Drywall pre-hang started at residential units Level 9