October 24-26, 2022

  • Deck shoring in progress at Level 21

  • Deck concrete placement at Level 21 to occur on 11/2/22

  • MEPF rough-in in progress at Level 21

  • Window Wall in progress at Level 13

  • Metal framing in progress at Level 12

  • Drywall pre-hang started at residential units Level 9