Deck shoring in progress at Level 22
Deck concrete placement at Level 21 to occur on 11/10/22
MEPF rough-in in progress through Level 21
Window Wall in progress at Level 14
Metal framing in progress at Level 12
Drywall pre-hang in progress at residential units Level 9