Deck shoring complete at Level 16
Deck concrete placement at Level 16 to occur on 9/21/22
MEPF rough-in continues throughout Level P5 - Level 16
Exterior glazing in progress at Level 8 and infill at lower levels
Metal framing in progress at Garage Level P5-Level 8
Tower crane jump completed on 9/15/22
top of page
bottom of page