September 26-30, 2022

  • Deck shoring in progress at Level 18

  • Deck concrete placement at Level 18 scheduled for 10/7/22

  • MEPF rough-in continues throughout Level P5 - Level 17

  • Exterior glazing in progress at Level 9

  • Metal framing in progress at Garage Level P5-Level 9

  • Trash chute installation complete at Levels 1 - 10