Deck shoring in progress at Level 18
Deck concrete placement at Level 18 scheduled for 10/7/22
MEPF rough-in continues throughout Level P5 - Level 17
Exterior glazing in progress at Level 9
Metal framing in progress at Garage Level P5-Level 9
Trash chute installation complete at Levels 1 - 10