September 4 - 8, 2023

  • Window Wall in progress at Level 37

  • Metal framing in progress at Level 35

  • Unit tape and finish in progress at Level 31

  • Unit paint in progress at Level 28

  • Unit cabinets in progress at Level 25

  • Unit Bath/Shower surround tile in progress at Level 26

  • Unit countertops in progress at Level 22

  • Unit LVP flooring in progress at Level 20

  • Rough clean in progress at Levell 12 Residential Units

  • Tree planting in production at Level 9 Amenity Deck

  • Pool deck installation in progress at Level 37