top of page


WHERE PASSION, PURPOSE,
& PROGRESS
MEET
We invite you to follow West's construction progress...
May 16-20, 2022
​
-
Deck Shoring in progress at Level 8 Area 2.
-
Rebar and MEP rough-in in progress at Level 8 Area 1.
-
Deck concrete placement at Level 8 Area 1 occurring on 05/24/22.
-
Rebar column cages and formwork in progress at Level 7 Area 3.
-
MEPF rough-in continues throughout Garage Level P5-Level 2.






May 9-13, 2022
​
-
Deck Shoring in progress at Level 8 Area 1.
-
Rebar and MEP rough-in in progress at Level 7 Area 3.
-
Deck concrete placement at Level 7 Area 3 occurring on 05/16/22.
-
Rebar column cages and formwork in progress at Level 7 Area 2.
-
MEPF rough-in continues throughout Garage Level P5-Level 2.
May 2-6, 2022
​
-
Deck Shoring in progress at Level 7 Area 3.
-
Rebar and MEP rough-in complete at Level 7 Area 2.
-
Deck concrete placement at Level 7 Area 1 occurring on 05/06/22.
-
Rebar column cages and formwork in progress at Level 7 Area 1.
-
MEPF rough-in continues throughout Garage Level P5-Level 2.






April 25-29, 2022
​
-
Deck Shoring in progress at Level 7 Area 2.
-
Rebar and MEP rough-in to start at Level 7 Area 2 on 05/02/22.
-
Deck concrete placement at Level 7 Area 1 scheduled for 04/29/22.
-
Rebar column cages and formwork in progress at Level 6 Area 3.
-
MEPF rough-in continues throughout Garage Level P5-Level 2.
April 18-22, 2022
​
-
Deck Shoring in progress at Level 7 Area 1.
-
Rebar and MEP rough-in to start at Level 6 Area 1 on 04/25/22.
-
Deck concrete placement at Level 7 Area 1 scheduled for 04/29/22.
-
Rebar column cages and formwork in progress at Level 6 Area 3.
-
MEPF equipment install in progress at Garage Level P5-Level 1.