  • Deck Shoring progressing at Level P1 Area 3

  • Rebar & MEP rough-in started at Level P1 Area 2

  • Concrete pour for Level P1 Area 2 scheduled for 10/12/21

  • Perimeter walls, columns & shear walls in progress at Level P1 Area 4

  • Waterproofing being installed up to grade at South elevation

  • CMU walls start installation at Garage Levels P4 & P5




  • Deck Shoring complete at Level P2-P1 ramp

  • Rebar & MEP rough in being installed at Level P2-P1 ramp

  • Concrete pour for Level P2 Area 4 scheduled for 9/29/21

  • Perimeter walls, columns & shear walls in progress at Level P2 Area 2

  • Waterproofing being installed up to grade at East elevation


  • Deck Shoring complete at Level P2

  • Rebar & MEP rough in being installed at Level P2 Area 3

  • Concrete pour for Level P2 Area 2 scheduled for 9/22/21

  • Perimeter walls, columns and shear walls in progress at Level P2 Area 1

  • Waterproofing being installed up to grade at Southeast elevation