  • Pool shower finishes in progress at Level 37

  • Tile flooring and backsplash ongoing at Level 9 Amenities

  • Wood ceiling furring and z clips installation ongoing in preparation for wood panel installation at Level 1 Lobby

  • Site work formwork and City elements in preparation for concrete placement along Union Street at Level 1 Exterior

  • P1 Mailroom and Dog Wash tile flooring in progress

  • Residential Unit owner punch list in progress thru Level 22