top of page
frank-mckenna-FNGWtVYvZ9Y-unsplash.jpg
West Logos-14 dropshadow.PNG

WHERE PASSION, PURPOSE,

& PROGRESS

MEET
We invite you to follow West's construction progress...
  • Pool fill was completed at Level 37

  • Countertops & backsplashes substantially complete in all Amenity areas

  • Penthouse appliances are going in on Levels 35-36

  • Wall stone at the Level 1 Lobby stairs ongoing

  • EV charging stations and parking control access gate installed in garage

  • Evening commissioning and life safety testing ongoing

  • Residential unit owner punch list in progress through Level 29


  • Millwork ongoing at Level 37 interior amenities

  • Began filling the pool & spa at Level 37 this week

  • Interior trim base and bath finishes in progress at Level 35-36 Penthouses

  • Audio/visual in progress at Level 9 Yoga Room

  • Handrails and MEP trim ongoing at Level 1 Lobby

  • P1 parcel pending mailbox installation began

  • Glass installed at Union Street canopy entry

  • Residential unit owner punch list in progress through Level 28




  • Cabinets began at the Level 37 interior amenities

  • Fireplace wall tile installation in progress at Level 37

  • Exterior gates, handrails and benches have been installed at Level 37

  • Flooring in progress at Penthouses Levels 35-36

  • Fire pit Installation ongoing at Level 9

  • Accent lighting and final MEP connections in progress at Level 1 Lobby

  • Concierge desk construction began at Level 1

  • Residential unit owner punch list in progress through Level 27 




bottom of page