Pool shower finishes in progress at Level 37
Tile flooring and backsplash ongoing at Level 9 Amenities
Wood ceiling furring and z clips installation ongoing in preparation for wood panel installation at Level 1 Lobby
Site work formwork and City elements in preparation for concrete placement along Union Street at Level 1 Exterior
P1 Mailroom and Dog Wash tile flooring in progress
Residential Unit owner punch list in progress thru Level 22
WHERE PASSION, PURPOSE,
& PROGRESS
MEET
We invite you to follow West's construction progress...
Pool paver installation began at Level 37 Exterior
pool shower finishes in progress at Level 37
Trellis wood slat installation in progress at Level 37 Exterior
Yoga Room flooring in progress at Level 9
Stone floor installation in progress at Level 1 Lobby
Site work at Union Street in progress at Level 1 Exterior
Mailbox installation in progress at P1
Punch list in progress at residential unit Levels 26-27
Paver waterproofing in progress at Level 37 Exterior
Climate control in progress at Level 37 Interior Amenity
Gym turf installed at Level 9 Exterior
Gym floor prep began at Level 9
Stone floor installation in progress at Level 1 Lobby
Partition door installation ongoing at Level 1 Lobby
Landscaping began within planters at Level 1 Exterior
Site work along Broadway in progress at Level 1 Exterior
Millwork in progress at P1 Mailroom
Dog Wash finishes in progress at P1
Punch list in progress at residential units 24-25
Office Elevator Lobby finishes in progress