Plumbing appliances going in at Level 37 restrooms
Ipe wood floor installed underneath lifeguard tower at Level 37
Flooring started at Penthouse Levels 35-36
Gym rubber flooring installation began at Level 9
Millwork is nearing substantial completion at Level 1 Lobby
Front St main entry doors and access pedestal installed at Level 1
Steel bollards installed along Union Street
Installation of security system began in P1 Mailroom and Dog Wash room
Residential unit owner punch list in progress thru Level 26