April 15 - 19, 2024

  • Plumbing appliances going in at Level 37 restrooms

  • Ipe wood floor installed underneath lifeguard tower at Level 37

  • Flooring started at Penthouse Levels 35-36

  • Gym rubber flooring installation began at Level 9

  • Millwork is nearing substantial completion at Level 1 Lobby

  • Front St main entry doors and access pedestal installed at Level 1

  • Steel bollards installed along Union Street

  • Installation of security system began in P1 Mailroom and Dog Wash room

  • Residential unit owner punch list in progress thru Level 26