April 29 - May 3, 2024

  • Millwork ongoing at Level 37 interior amenities

  • Began filling the pool & spa at Level 37 this week

  • Interior trim base and bath finishes in progress at Level 35-36 Penthouses

  • Audio/visual in progress at Level 9 Yoga Room

  • Handrails and MEP trim ongoing at Level 1 Lobby

  • P1 parcel pending mailbox installation began

  • Glass installed at Union Street canopy entry

  • Residential unit owner punch list in progress through Level 28