Millwork ongoing at Level 37 interior amenities
Began filling the pool & spa at Level 37 this week
Interior trim base and bath finishes in progress at Level 35-36 Penthouses
Audio/visual in progress at Level 9 Yoga Room
Handrails and MEP trim ongoing at Level 1 Lobby
P1 parcel pending mailbox installation began
Glass installed at Union Street canopy entry
Residential unit owner punch list in progress through Level 28